Administration and Research/ Colleges
Administration and Research/ Colleges

Fraunhofer IIS, Development Center X-ray Technology, Fürth - new construction

2010 - 2013

Construction data (without LINAC):
Effective area 5.282 m2
Gross floor area 10.321 m2
Gross room capacity 46.798 m3
Total construction costs app. € 23.800.000,-


Hans-Knöll-Institute (HKI), Jena - new construction

2009 - 2012

Construction data:
Effective area 2.577 m2
Gross floor area 6.175 m2
Gross room capacity 24.462 m3
Total construction costs app. € 19.040.000,-


Hessian Land Office of Criminal Investigation, Wiesbaden

2005 - 2011

Construction data:
Effective area 7.070 m2
Gross floor area 13.664 m2
Gross room capacity 50.336 m3
Total construction costs app. € 24.520.000,-


Biomedical Center of the University Hospital Bonn - new construction

2002 – 2011

Construction data:
Effective area 6.573 m2
Gross floor area 13.751 m2
Gross room capacity 51.303 m3
Total construction costs app. € 34.650.000,-


Fraunhofer IIS, Erlangen - new construction

1998 - 2008

Construction data:
Effective area 15.379 m2
Gross floor area 28.291 m2
Gross room capacity 105.377 m3
Total construction costs app. € 70.300.000,-


Fraunhofer IWM, Halle - new construction

2004 -2007

Construction data:
Shortlist at the architectural award of the federal state of Sachsen-Anhalt, 2007
Effective area 3.545 m2
Gross floor area 6.765 m2
Gross room capacity 33.705 m3
Total construction costs with initial equipment app. € 22.270.000,-


Zolltechnische Prüfungs- und Lehranstalt München - new construction

2002 -2006

Construction data:
Effective area 3.464 m2
Gross floor area 7.213 m2
Gross room capacity 31.824 m3
Total construction costs app. € 18.370.000,-


Fraunhofer IWU, Dresden - new construction

2002 – 2005

Construction data:
Effective area 4.083 m2
Gross floor area 7.111 m3
Gross room capacity 30.239 m3
Total construction costs € 14.640.000,-


Research Center for Environment and Health, Neuherberg/Munich

1996 - 2002

Construction data:
Effective area 1.970 m2
Gross floor area 4.198 m2
Gross room capacity 17.333 m3
Total construction costs app. € 9.710.000,-


Central Institute of the Medical Services of the Federal Armed Forces

1987 - 1998

Construction data:
Effective area 6.464 m2
Gross floor area 16.044 m2
Gross room capacity 62.000 m3
Total construction costs app. € 38.900.000,-


Fraunhofer ISIT, Itzehoe - new construction

1992 - 1995

Construction data:
Effective area 8.798 m2
Clean room capacity 2.000 m2
Gross floor area 29.433 m2
Gross room capacity 109.787 m3
Total construction costs app. € 85.600.000,-


Munich university of applied sciences in Pasing - reconstruction

1986 - 1995

Construction data for all 3 construction phases:
Effective area 16.672 m2
Gross floor area 27.443 m2
Gross room capacity 119.305 m3
Total construction costs app. € 32.420.000,-